Home
Edit Profile

Monthly Report: June 2025

Total hours: 535.61 hrs
Total payment: $13967.07
JONATHAN VARGAS
SEICO SERVICES
141:39 Tasks: 24
Payment: $3683.16
Adjust Time
Hourly Rate: $26.00
Project: SILVER SADDLE
Total hours: 140.65 hrs | Total payment: $3656.90
  • ACCES DOOR
    $208.00
  • CEILING GRID
    $1053.00
  • CEILING TILE
    $342.68
  • CLEANING
    $4.42
  • CORNER BEAD L BEAD
    $323.18
  • DOOR AND HARDWARE
    $750.62
  • DRYWALL
    $780.00
  • F R P
    $195.00
Project: Sin proyecto
Total hours: 1.00 hrs | Total payment: $26.00
  • DRYWALL
    $26.00
JUAN DAVID OYUELA
Q&V LABOR
125:37 Tasks: 19
Payment: $3140.75
Adjust Time
Hourly Rate: $25.00
Project: FBA GYM RENOVATIONS
Total hours: 8.00 hrs | Total payment: $200.00
  • CLEANING
    $200.00
Project: GRACE BRIDGE
Total hours: 0.00 hrs | Total payment: $0.00
  • INTERIOR FRAMING
    $0.00
Project: SILVER SADDLE
Total hours: 110.12 hrs | Total payment: $2753.00
  • BLOCKING
    $187.50
  • CEILING GRID
    $425.00
  • CEILING TILE
    $329.50
  • CLEANING
    $150.50
  • CORNER BEAD L BEAD
    $348.00
  • DRYWALL
    $1125.00
  • F R P
    $187.50
Project: Sin proyecto
Total hours: 7.50 hrs | Total payment: $187.50
  • DRYWALL
    $187.50
ARMANDO SANCHEZ
SEICO SERVICES
106:51 Tasks: 17
Payment: $3098.65
Adjust Time
Hourly Rate: $29.00
Project: 1517 ETAIN
Total hours: 28.05 hrs | Total payment: $813.45
  • DELIVERY
    $104.98
  • DRYWALL
    $224.75
  • INTERIOR FRAMING
    $232.00
  • PUNCH LIST
    $251.72
Project: FBA GYM RENOVATIONS
Total hours: 8.00 hrs | Total payment: $232.00
  • CLEANING
    $232.00
Project: GRACE BRIDGE
Total hours: 25.00 hrs | Total payment: $725.00
  • INTERIOR FRAMING
    $725.00
Project: KIDS SUNSHINE ROWLETT
Total hours: 23.00 hrs | Total payment: $667.00
  • DOOR AND HARDWARE
    $217.50
  • PUNCH LIST
    $449.50
Project: O'DONELL GARAGE
Total hours: 7.82 hrs | Total payment: $226.78
  • DRYWALL
    $226.78
Project: OFFICE
Total hours: 0.00 hrs | Total payment: $0.00
  • INTERIOR FRAMING
    $0.00
Project: SILVER SADDLE
Total hours: 7.50 hrs | Total payment: $217.50
  • DRYWALL
    $217.50
Project: SOLTERRA
Total hours: 7.50 hrs | Total payment: $217.50
  • ACCES DOOR
    $217.50
ISRAEL BERMUDEZ
SEICO SERVICES
101:56 Tasks: 20
Payment: $2956.26
Adjust Time
Hourly Rate: $29.00
Project: GRACE BRIDGE
Total hours: 49.32 hrs | Total payment: $1430.28
  • DELIVERY
    $246.50
  • DRYWALL
    $26.10
  • INTERIOR FRAMING
    $940.18
  • LAY OUT
    $217.50
Project: O'DONELL GARAGE
Total hours: 2.77 hrs | Total payment: $80.33
  • CEILING GRID
    $80.33
Project: OFFICE
Total hours: 7.50 hrs | Total payment: $217.50
  • CLEANING
    $217.50
Project: SILVER SADDLE
Total hours: 42.35 hrs | Total payment: $1228.15
  • BLOCKING
    $131.37
  • CEILING GRID
    $208.80
  • DELIVERY
    $29.87
  • DOOR AND HARDWARE
    $637.13
  • F R P
    $220.98
ARNOLD MURCIA
Q&V LABOR
34:29 Tasks: 5
Payment: $862.50
Adjust Time
Hourly Rate: $25.00
Project: GRACE BRIDGE
Total hours: 34.50 hrs | Total payment: $862.50
  • INTERIOR FRAMING
    $675.00
  • LAY OUT
    $187.50
LUIS ANGEL VAZQUEZ
Q&V LABOR
15:59 Tasks: 2
Payment: $0.00
Adjust Time
Hourly Rate: $0.00
Project: GRACE BRIDGE
Total hours: 16.00 hrs | Total payment: $0.00
  • DRYWALL
    $0.00
  • INTERIOR FRAMING
    $0.00
JAIME CIPRIANO
Q&V LABOR
08:29 Tasks: 1
Payment: $212.50
Adjust Time
Hourly Rate: $25.00
Project: GRACE BRIDGE
Total hours: 8.50 hrs | Total payment: $212.50
  • INTERIOR FRAMING
    $212.50
LUIS SANTAFE
SEICO SERVICES
00:31 Tasks: 1
Payment: $13.25
Adjust Time
Hourly Rate: $25.00
Project: PARTY BLOCK
Total hours: 0.53 hrs | Total payment: $13.25
  • CLEANING
    $13.25
RAYMUNDO TORRES
Q&V LABOR
00:00 Tasks: 1
Payment: $0.00
Adjust Time
Hourly Rate: $0.00
Project: GRACE BRIDGE
Total hours: 0.00 hrs | Total payment: $0.00
  • DRYWALL
    $0.00
REY TORRES
Q&V LABOR
00:00 Tasks: 1
Payment: $0.00
Adjust Time
Hourly Rate: $0.00
Project: GRACE BRIDGE
Total hours: 0.00 hrs | Total payment: $0.00
  • DRYWALL
    $0.00
Employee Company Total Time Payment ($) Actions
JONATHAN VARGAS
24 tasks
SEICO SERVICES
141:39
141.66 hours
$3683.16 Adjust Time
Hourly Rate: $26.00
Project: SILVER SADDLE
Total: 140.65 hrs $3656.90
Task Hours Payment
ACCES DOOR 8.00 $208.00
CEILING GRID 40.50 $1053.00
CEILING TILE 13.18 $342.68
CLEANING 0.17 $4.42
CORNER BEAD L BEAD 12.43 $323.18
DOOR AND HARDWARE 28.87 $750.62
DRYWALL 30.00 $780.00
F R P 7.50 $195.00
Project: Sin proyecto
Total: 1.00 hrs $26.00
Task Hours Payment
DRYWALL 1.00 $26.00
JUAN DAVID OYUELA
19 tasks
Q&V LABOR
125:37
125.63 hours
$3140.75 Adjust Time
Hourly Rate: $25.00
Project: FBA GYM RENOVATIONS
Total: 8.00 hrs $200.00
Task Hours Payment
CLEANING 8.00 $200.00
Project: GRACE BRIDGE
Total: 0.00 hrs $0.00
Task Hours Payment
INTERIOR FRAMING 0.00 $0.00
Project: SILVER SADDLE
Total: 110.12 hrs $2753.00
Task Hours Payment
BLOCKING 7.50 $187.50
CEILING GRID 17.00 $425.00
CEILING TILE 13.18 $329.50
CLEANING 6.02 $150.50
CORNER BEAD L BEAD 13.92 $348.00
DRYWALL 45.00 $1125.00
F R P 7.50 $187.50
Project: Sin proyecto
Total: 7.50 hrs $187.50
Task Hours Payment
DRYWALL 7.50 $187.50
ARMANDO SANCHEZ
17 tasks
SEICO SERVICES
106:51
106.85 hours
$3098.65 Adjust Time
Hourly Rate: $29.00
Project: 1517 ETAIN
Total: 28.05 hrs $813.45
Task Hours Payment
DELIVERY 3.62 $104.98
DRYWALL 7.75 $224.75
INTERIOR FRAMING 8.00 $232.00
PUNCH LIST 8.68 $251.72
Project: FBA GYM RENOVATIONS
Total: 8.00 hrs $232.00
Task Hours Payment
CLEANING 8.00 $232.00
Project: GRACE BRIDGE
Total: 25.00 hrs $725.00
Task Hours Payment
INTERIOR FRAMING 25.00 $725.00
Project: KIDS SUNSHINE ROWLETT
Total: 23.00 hrs $667.00
Task Hours Payment
DOOR AND HARDWARE 7.50 $217.50
PUNCH LIST 15.50 $449.50
Project: O'DONELL GARAGE
Total: 7.82 hrs $226.78
Task Hours Payment
DRYWALL 7.82 $226.78
Project: OFFICE
Total: 0.00 hrs $0.00
Task Hours Payment
INTERIOR FRAMING 0.00 $0.00
Project: SILVER SADDLE
Total: 7.50 hrs $217.50
Task Hours Payment
DRYWALL 7.50 $217.50
Project: SOLTERRA
Total: 7.50 hrs $217.50
Task Hours Payment
ACCES DOOR 7.50 $217.50
ISRAEL BERMUDEZ
20 tasks
SEICO SERVICES
101:56
101.94 hours
$2956.26 Adjust Time
Hourly Rate: $29.00
Project: GRACE BRIDGE
Total: 49.32 hrs $1430.28
Task Hours Payment
DELIVERY 8.50 $246.50
DRYWALL 0.90 $26.10
INTERIOR FRAMING 32.42 $940.18
LAY OUT 7.50 $217.50
Project: O'DONELL GARAGE
Total: 2.77 hrs $80.33
Task Hours Payment
CEILING GRID 2.77 $80.33
Project: OFFICE
Total: 7.50 hrs $217.50
Task Hours Payment
CLEANING 7.50 $217.50
Project: SILVER SADDLE
Total: 42.35 hrs $1228.15
Task Hours Payment
BLOCKING 4.53 $131.37
CEILING GRID 7.20 $208.80
DELIVERY 1.03 $29.87
DOOR AND HARDWARE 21.97 $637.13
F R P 7.62 $220.98
ARNOLD MURCIA
5 tasks
Q&V LABOR
34:29
34.50 hours
$862.50 Adjust Time
Hourly Rate: $25.00
Project: GRACE BRIDGE
Total: 34.50 hrs $862.50
Task Hours Payment
INTERIOR FRAMING 27.00 $675.00
LAY OUT 7.50 $187.50
LUIS ANGEL VAZQUEZ
2 tasks
Q&V LABOR
15:59
16.00 hours
$0.00 Adjust Time
Hourly Rate: $0.00
Project: GRACE BRIDGE
Total: 16.00 hrs $0.00
Task Hours Payment
DRYWALL 8.00 $0.00
INTERIOR FRAMING 8.00 $0.00
JAIME CIPRIANO
1 tasks
Q&V LABOR
08:29
8.50 hours
$212.50 Adjust Time
Hourly Rate: $25.00
Project: GRACE BRIDGE
Total: 8.50 hrs $212.50
Task Hours Payment
INTERIOR FRAMING 8.50 $212.50
LUIS SANTAFE
1 tasks
SEICO SERVICES
00:31
0.53 hours
$13.25 Adjust Time
Hourly Rate: $25.00
Project: PARTY BLOCK
Total: 0.53 hrs $13.25
Task Hours Payment
CLEANING 0.53 $13.25
RAYMUNDO TORRES
1 tasks
Q&V LABOR
00:00
0.00 hours
$0.00 Adjust Time
Hourly Rate: $0.00
Project: GRACE BRIDGE
Total: 0.00 hrs $0.00
Task Hours Payment
DRYWALL 0.00 $0.00
REY TORRES
1 tasks
Q&V LABOR
00:00
0.00 hours
$0.00 Adjust Time
Hourly Rate: $0.00
Project: GRACE BRIDGE
Total: 0.00 hrs $0.00
Task Hours Payment
DRYWALL 0.00 $0.00

Showing 1 to 10 of 10 results